Fifty Years of Metro, and the Biggest Expansion Since 1975

South America’s second metro celebrated its 50th anniversary in 2025 — 7 lines, 143 stations, 149 km, 640 million journeys a year — and marked it by building three new lines at once. Lines 7, 8 and 9 plus the airport light rail will make Santiago’s the longest metro in Latin America by 2033.

October 2026 · TIO Metropolises Desk
640M+
metro journeys in 2024 — ~2.1 million on an average weekday across 7 lines, 143 stations and 149 km (Metro de Santiago)
26 km
Line 7, under construction (40–42% complete): 19 stations Renca→Vitacura, $2.53B, opening 2028 — first metro for three communes, 1.6M beneficiaries
+82.5 km
network growth by 2033 — Lines 7, 8, 9 and A plus extensions: 231.5 km and 199 stations, set to be Latin America’s longest metro
160 km/h
top speed of EFE’s new CRRC bimodal trains on Santiago–Chillán (397 km in ~3 hours) — the most advanced passenger train in South America

Line 7 and the airport train

Line 7 is the flagship: 26 km fully underground from Renca to Vitacura, 19 stations, $2.53 billion, opening late 2028. It gives Renca, Cerro Navia and Vitacura their first metro, relieves Line 1 by ~10,000 daily passengers, and runs on 37 driverless Alstom trains built in Taubaté, Brazil. Lines 8 (Providencia–Puente Alto, $1.9B, 2032–33) and 9 (into La Pintana, $2.73B, staged 2030–2033) follow; Line 9’s Cal y Canto station will be the first in the Americas where four metro lines meet. President Boric added Line A in June 2025 — a light rail linking the airport to Line 7’s Huelén station.

The metro’s daily miracle is the bip! card integrating metro, buses and MetroTren commuter rail in a single fare. The system carries about 46% of all public-transport trips in a city of 6.2 million — and it survived the 2019 social outbreak that torched stations, rebuilt, and kept every expansion date credible. Alstom, supplier of 75% of the rolling stock, marked 50 years of partnership in October 2025 — from the first 1975 trains to the autonomous Line 7 fleet.

EFE’s quiet renaissance

The state railway EFE set its own record in 2025: 32 million passengers, with losses cut by more than 70 billion pesos. EFE Central led with 14.47 million (+5.6%), powered by the Chillán corridor, where six CRRC Sifang bimodal trainsets — 238 seats, 160 km/h, electric or diesel — have run since 2024 as the most modern passenger trains on the continent. The express covers the 397 km to Chillán in about three hours, three pairs a day.

The Santiago–Batuco commuter line and the Melipilla extension are in construction, the Tren Nocturno to Temuco keeps the overnight tradition alive as a tourist service, and Puerto Montt regained trains in 2025 as a pilot. Chile’s rail map remains a spine, not a net — but for the first time in decades the spine is growing vertebrae in both directions from Estación Central, Santiago’s 1897 landmark terminus.

THE TIO READ
The reviewer’s call

The TIO Read: Santiago is the only city in this series where the metro is simultaneously a heritage system (1975), a social-pressure valve (2019) and the continent’s most ambitious build site (three lines at once) — and still runs 87%-style reliability through all three identities. The reviewer’s call: ride Line 1 at rush hour once to understand the city’s load, then time a 2028–29 return for the Line 7 + airport-rail opening — that pairing reprices the entire northwest; on EFE, the Chillán express is the best rail argument in South America right now — three hours, bimodal, and cheaper than the bus it beats.