RAIL HUB · RIO DE JANEIRO

A Metro Deal, a Rail Tender, and a Tram That Never Needed Wires

Rio moves on three rail systems: a metro that just traded a concession extension for the resurrection of Gávea station, a 270-km commuter network heading to auction after its operator’s collapse — and the VLT, the catenary-free tram that stitches the bus terminal, the port and Santos Dumont into one fare.

October 2026 · TIO Metropolises Desk
2048
new end date of the MetrôRio concession after the April 2025 deal: the state added ten years in exchange for the concessionaire finishing Gávea station — R$600M from MetrôRio plus R$97M from the state (Rio State Government)
Jul 2028
target opening of Gávea station on Line 4, where construction resumed in August 2025 after a decade abandoned and 36 million litres of floodwater pumped out (MetrôRio)
750k
daily passengers on SuperVia’s 270 km, five-line commuter network — now in judicial recovery, with a new operator to be chosen at auction on 27 January 2026 under a pay-per-kilometre model (Setram / IRJ)
88M+
passengers carried by the VLT Carioca tram in its first six years — 32 Alstom Citadis vehicles powered through the track (APS), the world’s second fully catenary-free system after Dubai (Alstom)

The metro trades time for steel

MetrôRio — majority-owned by Mubadala since 2021 — runs what is effectively a two-line network (Lines 1/4 interlined over 32 km; Line 2 over 30.2 km), Brazil’s second-busiest metro. The April 2025 agreement extends the concession to 2048 and folds Line 4 into MetrôRio from the old Rio Barra consortium; in return the concessionaire must deliver Gávea, the station abandoned mid-dig in 2015 and flooded for structural safety.

Work resumed in August 2025; a shuttle between São Conrado and Gávea is targeted for July 2028, eventually becoming the interchange that de-interlines Lines 1 and 4. Fares moved to R$7.90 in April 2025 — above the bus, a structural problem in a city where rail ridership, unlike Brazil’s average, is still shrinking.

Commuter rail gets a restart; the tram just grows

SuperVia’s five lines carry ~750,000 people a day with 201 EMUs, but the operator is in judicial recovery under Guarana Urban Mobility. The state’s January 2026 tender will pay the new operator per kilometre run — not per passenger — after R$160 million of state investment in cable replacement and refurbishment cut the copper-theft disruptions that plagued the network.

The bright spot is municipal: the VLT Carioca, opened for the 2016 Olympics, links the Novo Rio bus terminal, the port’s cruise pier, Central do Brasil and Santos Dumont airport across 29 stops. Ridership jumped 30% year on year in January 2025 after the Gentileza Intermodal Terminal tied the tram into the BRT; at R$4.70 it costs the same as a city bus and runs on 100% renewable power.

THE TIO READ
The reviewer’s call

The TIO read: Rio’s rail story is two fixes and one success. The Gávea deal is genuinely good policy — the city traded concession years for a station that unlocks Line 4’s logic. SuperVia’s tender is the swing factor for 2026. For visitors, the VLT is the answer: one R$4.70 ride from the cruise pier or Novo Rio to the Santos Dumont doorstep.